What this code requires
CMC 802.6.1 is the California Mechanical Code section that sets where gas vents terminate. A listed-cap vent 12 inches or smaller and at least 8 feet from a vertical wall terminates at the roof-pitch height in Table 802.6.1; larger vents or vents closer to a wall must end at least 2 feet above the roof penetration and 2 feet above anything within 10 feet. Through-the-wall terminals follow the clearances in CMC 802.8 and Table 802.8.1, and chimneys follow 802.5.4. Furnaces, water heaters, boilers, and direct-vent fireplaces are the most common permits flagged.
How to fix it
Pull the applicable termination rule from CMC 802.6.1 or 802.8
In the 2025 CMC, 802.5 covers chimneys; gas vents terminate per 802.6.1 and through-the-wall terminals per 802.8. A listed-cap gas vent 12 inches or smaller and at least 8 feet from a vertical wall uses Table 802.6.1, which sets height by roof pitch. Direct-vent and other wall terminals use the clearances in Table 802.8.1. Write down the specific rule and the required dimensions — you will call these out on the plans in the next steps.
Dimension the vent termination height above the roof
On the roof plan or the building section, add a callout showing the vent pipe termination height above the roof. Vents over 12 inches, or within 8 feet of a vertical wall, must terminate at least 2 feet above the highest point where they pass through the roof and 2 feet above any part of the building within 10 feet; smaller vents use Table 802.6.1 by roof pitch. Label the dimension in inches, include an arrow pointing to the termination, and note the CMC table number you are referencing. A single clear callout eliminates most plan-check questions on this section.
Show clearances from windows, doors, and openings on the elevation sheet
On the exterior elevation sheet, draw a dashed line from the vent terminal to each nearby window, door, and gravity air inlet within the clearance zone. Dimension each gap. CMC Table 802.8.1 sets these clearances: 6 to 12 inches from an openable window or door for direct-vent terminals by input, 4 feet below or beside (1 foot above) for non-direct terminals, and 10 feet horizontally or 3 feet above a mechanical air inlet. If your site is tight and a clearance looks marginal, add a note stating the measured distance and the code minimum. Plan-checkers approve details that show the work was done — leaving it to the reviewer to calculate guarantees a comment.
Detail the direct-vent exterior-wall terminal if applicable
For direct-vent appliances terminating through an exterior wall instead of the roof, add a detail on the exterior elevation showing the concentric terminal location, its height above grade (minimum 12 inches above finished grade, porch, or deck), its clearance from nearby openable windows and doors, and any corner clearance the manufacturer specifies (Table 802.8.1 sets none of its own). Note the terminal model or manufacturer if it is a manufacturer-listed assembly, because some local AHJs want confirmation that the terminal is listed for the appliance. A 1/4 inch = 1 foot detail callout on A3 or M2 works well.
Address chimney cap or spark-arrestor restrictions for masonry vents
If the vent is a chimney or a gas vent with a cap or shroud, draw a detail of the termination. Vents may not discharge into a space enclosed by screens with openings smaller than 1/4 inch (CMC 802.1.2), and decorative shrouds are not allowed unless listed for that system (CMC 802.5.4.3). A fine bird screen or unlisted decorative cap is a common flag. Note the mesh size and the cap or shroud listing so the plan-checker can verify it at a glance.
Cross-reference the mechanical schedule to the sheet showing the termination
Add a note in the mechanical equipment schedule pointing to the sheet and detail number where the termination callout lives. Something like Vent termination per CMC 802.6.1 — see A3/detail 4. This cross-reference prevents the plan-checker from approving the mechanical sheet and then flagging the architectural sheet separately. It also helps on re-submittals: the reviewer can jump directly to the corrected detail without hunting through the set.
Write the correction response letter citing the specific sub-section
When you respond to a vent termination comment, title your response with the exact comment number and code reference. State which table row applies to your appliance, the required dimension, and what the revised plans show. Reviewers on tight schedules skim response letters first and then verify in the drawings. A response that matches the comment number to a specific plan sheet and detail number closes the loop cleanly and reduces the chance of the same comment coming back on the next cycle.
Take the CMC 802.6.1 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Here is why plan-checkers flag CMC 802.6.1 most often on residential gas-appliance permits.
The most common reason is that the vent termination height above the roof is not called out on the mechanical plans at all. If the sheet just shows a vent pipe symbol exiting the roof without a dimension or a note referencing the code table, the plan-checker has no way to verify compliance and will flag it. This happens most on water-heater replacements where the contractor is working off an existing roof penetration and assumes the prior installation was correct.
A second scenario is clearance from openings. A roof vent has to end at least 3 feet above a forced air inlet within 10 feet (CMC 802.6.1), and a through-the-wall terminal has to meet the window, door, and air-inlet clearances in Table 802.8.1. In dense urban lots with two-story additions, the vent from a first-floor furnace can end up uncomfortably close to a second-floor bedroom window. If the elevation sheet does not show those clearances explicitly, expect a flag.
Chimneys and caps get flagged on a different sub-issue. A chimney for residential-type appliances must extend at least 3 feet above the roof penetration and 2 feet above any part of the building within 10 feet (CMC 802.5.4). Gas vents must end in a listed cap or listed roof assembly, decorative shrouds are allowed only where listed for the system, and vents cannot discharge into a space enclosed by screens finer than 1/4 inch. Sketching the cap detail saves a round of questions.
Direct-vent appliances have their own column in CMC Table 802.8.1, with clearances for the wall terminal that scale with appliance input. These often terminate through an exterior wall rather than the roof, which catches contractors off guard. If the floor plan shows the appliance but the exterior elevation does not mark the terminal location and its clearance from grade, the correction will ask for it.