What this code requires
CMC 310.1 is the California Mechanical Code section that requires condensate from air-cooling coils, condensing appliances, and similar equipment to be collected and discharged to an approved plumbing fixture or disposal area, through an indirect waste pipe sloped at least 1/8 inch per foot and sized per Table 310.3. Where the equipment sits in a space that overflow could damage, CMC 310.2 adds a second layer of protection. This section is cited on nearly every residential and light-commercial HVAC permit where condensate drainage details are missing or incomplete on the submitted drawings.
How to fix it
Show the primary condensate drain line and discharge point on the mechanical plan
On the mechanical plan sheet, draw the primary condensate drain line from the air handler to its discharge point. Label it as the primary condensate drain. Identify the discharge point explicitly, such as the sanitary sewer via an indirect waste receptor (air gap required), an approved floor drain, or an approved exterior disposal area that will not pool near the foundation or drain over a public way. The plan-checker needs to see the start point, pipe routing, and end point to confirm the line is code-compliant. A note that says "drain to outside" is not sufficient without showing the route and the termination point.
Specify the primary drain pipe diameter and minimum slope
Call out the primary drain pipe diameter and the slope on the plan or in a mechanical schedule. Table 310.3 sets the minimum size by capacity: 3/4 inch up to 20 tons, which covers most residential split systems, and PVC is permitted below 1-1/4 inches. The run must slope at least 1/8 inch per foot toward the discharge point. If the line has to travel a long horizontal distance, confirm the slope is maintainable along the entire run before finalizing the routing. When the plan omits pipe size and slope, the reviewer has no compliance path to check against and will send a correction asking for both.
Add secondary overflow protection for attic and ceiling-mounted air handlers
For any air handler installed in an attic, above a finished ceiling, or anywhere a primary drain blockage would cause water damage to occupied space or structure, you must provide secondary overflow protection. CMC 310.2 offers four options: a water-level device that shuts the unit off, a watertight secondary pan with its own drain, a secondary drain line set above the primary connection, or a pan with a water-level shutoff. Added drain lines must be at least 3/4 inch and discharge where readily observed. Show whichever method you are using on the plan. If using a secondary pan, note the pan dimensions, the pan drain line size, and the discharge point. If using a secondary drain line terminating outside, show the termination point on an exterior elevation.
Show the condensate pump and overflow safety switch when gravity drainage is not possible
When the air handler sits below the approved discharge point and gravity flow is not possible, a condensate pump can be used where the Authority Having Jurisdiction approves it. Show the pump location on the mechanical plan and call out the pump capacity in gallons per hour. Note the discharge line routing from the pump to the approved discharge point. CMC 310.1.1 requires the pump discharge to rise to a gravity drain and each unit to have its own sump interlocked to keep the equipment from running during a failure. Show the float switch and its connection to the system control circuit on the plan. A pump alone does not satisfy the secondary protection requirement.
Verify the discharge location qualifies under CMC 310
Confirm the discharge point you have shown is an approved plumbing fixture or disposal area. Into the drainage system, CMC 310.5 requires an indirect connection through an air gap or air break to a trapped and vented receptor, dry well, mop sink, leach pit, or fixture tailpiece. Condensate cannot drain over a public way, and an attic without a receptor is not a disposal area. Some cities have local amendments that further restrict exterior condensate discharge, particularly in water-sensitive areas. Check the adopted local amendments for your jurisdiction before finalizing the discharge point.
Add a condensate drainage note to the mechanical plan or schedule
Add a note on the mechanical sheet that explicitly references the key items: primary drain destination, secondary overflow method, pipe sizes, and slope. Something like: "Condensate drainage per CMC 310. Primary 3/4-inch PVC drain to [location]. Secondary overflow pan/drain to [readily observed location]. All horizontal runs at 1/8-inch per foot minimum slope." This gives the plan-checker a checklist they can verify against the section without hunting through the plan set. It also documents the design intent for the inspector at rough-in.
Take the CMC 310.1 fix steps with you
All 6 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Plan-checkers flag CMC 310.1 most often when the mechanical plan shows the air handler location but says nothing about where the condensate goes. The drainpipe destination has to be called out explicitly on the drawings. Writing "condensate per code" in a note does not cut it. The reviewer needs to see the line routing and the approved discharge point before they can sign off.
A second common trigger is the missing secondary drain or overflow pan. CMC 310.2 requires an additional overflow protection method when the equipment is installed where condensate overflow could cause damage, which covers almost every attic or ceiling-mounted air handler. Plans that show only the primary drain get a correction asking for the secondary pan or secondary drain line, whichever applies to the installation.
Undersized or unspecified primary drain lines also draw corrections. Table 310.3 sets the minimum pipe size by cooling capacity (3/4 inch up to 20 tons, 1 inch from 21 to 40 tons), and CMC 310.1 requires a slope of at least 1/8 inch per foot. When the plan shows a drain line without specifying size or slope, the reviewer has no way to confirm compliance and kicks it back.
Finally, the discharge location itself matters. Condensate has to go to an approved plumbing fixture or disposal area, and it cannot drain over a public way. Where it connects to the drainage system, CMC 310.5 requires an indirect connection through an air gap or air break to a trapped and vented receptor, dry well, mop sink, leach pit, or fixture tailpiece. If the plans route condensate somewhere that does not qualify, you will get a correction calling for a redesign of the discharge point.
The official code
2025 California Mechanical Code Section 310 Condensate Wastes and Control (310.1 Condensate Disposal), via California Building Standards Commission
Read the source →