What this code requires
CEC 210.11(C) is the California Electrical Code section that requires every dwelling to have dedicated branch circuits for small appliances, laundry, and bathrooms — separate from the general lighting circuits. At minimum, the code calls for two 20-amp small-appliance circuits in the kitchen and dining area, one 20-amp laundry circuit, and one 20-amp bathroom circuit. These circuits can't be shared with lighting loads or other rooms. Most single-family residential and ADU electrical plans get flagged when these circuits are missing from the panel schedule or load calculation.
How to fix it
Audit your panel schedule for the required circuits
Pull your panel schedule and look for: (1) two separate 20-amp breakers labeled for small-appliance use in the kitchen/dining area, (2) one 20-amp breaker labeled exclusively for laundry, (3) one 20-amp breaker labeled for bathroom receptacles, and (4) where there is a garage with power, one 20-amp garage receptacle breaker per 210.11(C)(4). If any of these are missing, combined with other loads, or not at 20 amps, mark them for revision before resubmitting. This is a quick scan — most corrections can be spotted in under five minutes on the panel schedule.
Add two dedicated 20-amp small-appliance circuits
CEC 210.11(C)(1) requires at least two 20-amp small-appliance branch circuits for receptacle outlets in the kitchen, pantry, breakfast room, and dining room. Each circuit must be a dedicated 20-amp breaker — 15-amp is not acceptable here. Update the panel schedule to show two breakers labeled 'Kitchen Small Appliance 1' and 'Kitchen Small Appliance 2' (or equivalent). Note on the plans that these circuits supply only kitchen and dining area receptacles — no lighting loads, no other rooms.
Add a dedicated 20-amp laundry circuit
CEC 210.11(C)(2) requires one 20-amp branch circuit for laundry receptacle outlets. This circuit must serve only the laundry area — it cannot supply any other outlets or lighting loads. Add a 20-amp breaker to your panel schedule labeled 'Laundry.' On the floor plan, show the laundry receptacle connected to this dedicated circuit. If the laundry room is shared with another room (like a hallway closet), make clear in the notes that the circuit only serves the laundry receptacle.
Add a dedicated 20-amp bathroom circuit
CEC 210.11(C)(3) requires at least one 20-amp circuit for bathroom receptacle outlets. The circuit can supply receptacle outlets in multiple bathrooms, but it cannot supply outlets outside any bathroom — no hallway outlets, and no lighting unless the circuit serves only a single bathroom. Add a 20-amp breaker labeled 'Bathroom Receptacles.' If you have two bathrooms fed from this single circuit, add a note on the electrical plan clarifying that all outlets on this breaker are bathroom receptacles only. This avoids a second correction.
Update the load calculation to reflect the new circuits
When you add dedicated circuits, your load calculation changes. Update the load calc sheet to include the small-appliance circuits at 1,500 VA each (that's the standard NEC/CEC demand load per 20-amp small-appliance circuit), plus the laundry circuit at 1,500 VA. These are required loads under CEC Article 220 — they must appear in the calculation even if the actual connected load is lower. Skipping this step on a resubmit often triggers a second correction on the load calculation sheet.
Label circuits clearly on the floor plan
Plan-checkers cross-reference the panel schedule against the floor plan. Make sure each required circuit has a corresponding circuit identifier on the floor plan (e.g., 'SA-1', 'SA-2', 'LY', 'BA') and that those identifiers match the panel schedule exactly. If the floor plan shows receptacles without circuit labels, or if labels don't match the panel schedule, the checker will flag the discrepancy. A clean, cross-referenced set is the fastest path through plan check.
Verify compliance for ADUs and accessory structures
ADUs are dwelling units under the code and must meet the same 210.11(C) requirements as the main house. A kitchen in an ADU requires two dedicated 20-amp small-appliance circuits. If the ADU has a laundry hook-up, add a dedicated 20-amp laundry circuit. If it has a bathroom, add a dedicated 20-amp bathroom circuit. These can't share a panel or breaker with the main house. Many ADU plan sets get flagged because the plans were adapted from a room addition template that doesn't include a full kitchen or laundry — check this before you submit.
Take the CEC 210.11(C) fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Here's why plan-checkers flag this section. The most common trigger is a panel schedule that doesn't show the three required circuits as separate, dedicated breakers. Some contractors list a single 'kitchen circuit' on the plan without splitting out the two required 20-amp small-appliance circuits — the plan-checker sees one line item where there should be two, and the correction goes out.
The second common scenario is a laundry circuit that's shared with a lighting or receptacle circuit elsewhere in the house. CEC 210.11(C)(2) requires the laundry circuit to serve only that space — nothing else rides on it. If your panel schedule shows 'Laundry/Hallway lights' on a single 20-amp breaker, that's a correction. Same issue comes up in ADU plans when the laundry hook-up is added at the last minute and the drafter doesn't add a dedicated breaker.
Bathroom circuits get flagged for a similar reason. CEC 210.11(C)(3) requires at least one 20-amp circuit for bathroom receptacles, and it can't supply any outlets outside the bathroom. If your plan shows bath receptacles sharing a circuit with a hallway outlet or a lighting circuit, that's a red flag. Multi-bathroom layouts sometimes have one circuit feeding two bathrooms — that's allowed under the code if all the outlets on the circuit are in bathrooms, but the plan has to make that clear or the checker will flag it.
On remodel and addition permits, the correction often surfaces because the existing panel schedule on the as-built drawings doesn't reflect the required circuits. Even if the circuits exist in the field, the plan-checker needs to see them documented. If the electrical plans were drawn from a template that doesn't include a panel schedule, or if the panel schedule was copied from the original permit without updates, the dedicated circuits may simply not appear.