What this code requires
CRC R403.1 sets the minimum requirements for continuous concrete footings under light-frame walls in California residential construction. Footings must be sized based on soil bearing capacity and the load they carry, with a minimum width of 12 inches and thickness of 6 inches for one-story buildings. The section also requires horizontal rebar reinforcement in both the top and bottom of the footing, anchor bolts at specified spacing with adequate embedment into the concrete, and plate washers where anchor bolts attach to the mudsill. In Seismic Design Categories D0, D1, and D2, which cover most of Orange County, the requirements get more specific on rebar size and placement.
How to fix it
Show footing dimensions on the foundation plan
On your foundation plan, call out the footing width and thickness explicitly for each wall condition. For a single-story wood frame wall, minimum is 12 inches wide by 6 inches thick assuming 1,500 psf soil bearing. For two stories with a crawl space, minimum is 15 inches wide by 6 inches thick. For three stories with a crawl space, 18 inches wide by 6 inches thick. Don't rely on a general note buried in specs — the plan-checker wants to see it dimensioned directly on the foundation plan, referenced back to a keyed detail. If you're using a geotechnical report, note the report number and the bearing value you're designing to.
Add rebar callouts to the footing section detail
Include a footing section detail at 1/4 inch equals 1 foot scale or larger that shows one No. 4 horizontal bar at the top and one at the bottom of the footing (with a stem wall: one within 12 inches of the top of the wall and one 3 to 4 inches from the bottom of the footing). Call out bar size, quantity, and placement. Show cover dimensions: 3 inches minimum where concrete is cast against earth, and 1-1/2 inches for No. 5 and smaller bars in formed concrete exposed to earth or weather. If the footing is deeper than the code minimum, your detail should still show both bars in the correct zones. Plan-checkers in OC jurisdictions will fail rebar review if the detail is vague or missing.
Dimension anchor bolt spacing and end-of-plate placement
On the foundation plan or a dedicated anchor bolt plan, show spacing at 6 feet on center maximum. Then add a separate note specifically calling out that bolts are placed within 12 inches of the end of every mudsill plate piece and within 12 inches of any splice or corner. If you have a 20-foot wall where 6-foot spacing works in the field, your end bolt may still be 18 inches from the plate end — that's a correction. Mark the end-of-plate bolt locations explicitly so the plan-checker can verify without measuring. On remodels tying into existing foundations, field-verify actual bolt locations and document them on the drawings before submittal.
Specify 7-inch minimum embedment in the footing detail
Anchor bolt embedment into concrete must be at least 7 inches, measured into the concrete, not through the sill plate. Show this dimension with a leader or dimension line in your footing section detail. Also call out the bolt diameter (1/2 inch or 5/8 inch is typical) and total bolt length so the inspector can verify during concrete placement. Bolts with less than 7 inches of embedment are a field rejection, not just a plan check comment — that means pulling permits for a repair pour if they're set short. Don't skip this callout.
Add 3x3 plate washer spec for SDC D seismic zones
In Seismic Design Categories D0, D1, and D2, standard cut washers are not code-compliant at anchor bolts along braced wall lines. Your footing detail and general notes must call out 3-inch by 3-inch by 0.229-inch (7-gauge) square plate washers at every anchor bolt in required braced wall lines (cut washers are allowed only in wall lines with no braced wall panels). Standard hardware-store washers are not acceptable substitutes. Add this callout to the footing detail section, the mudsill connection detail, and the general structural notes. If you're using a prefabricated anchor strap or hold-down instead of a conventional J-bolt, verify the product's ICC evaluation report specifies an equivalent washer or bearing plate.
Reference soil bearing capacity or geotechnical report
R403.1 ties footing sizing to soil bearing capacity. If you're using the presumptive bearing value, your general notes should state something like: 'Footings designed for 1,500 psf presumptive soil bearing capacity per Table R401.4.1(1). No geotechnical investigation on file.' If the project required a soils report, note the report title, author, and date on the foundation plan sheet, and confirm your footing sizing matches the report's recommended bearing value. Anaheim and Irvine plan-checkers frequently request this reference on the sheet, especially for ADUs with grading.
Verify footing detail matches structural engineer's plan
If you have a structural engineer of record, confirm their footing schedule matches what the architectural foundation plan shows. Discrepancies between sheets are a common cause of corrections — the plan-checker will compare them. If the structural plan governs, note that on the architectural sheet and cross-reference the structural detail number. If the structural plan shows a larger footing or additional rebar than R403.1 minimums, the structural plan controls. Submitting conflicting sheets creates questions that slow the review even if both sheets are technically correct.
Take the CRC R403.1 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
The most common reason plan-checkers flag R403.1 is that the foundation plan doesn't show enough detail to verify compliance. If your drawings just show a generic footing without calling out rebar size and placement, bolt spacing, or embedment depth, the plan-checker has no way to approve it. A note that says "footings per code" doesn't cut it.
Rebar callouts are a frequent miss. In SDC D0, D1 and D2, R403.1.3 requires at least one No. 4 bar near the top and one near the bottom of continuous footings. A lot of plans show the footing width and depth correctly but skip the rebar detail entirely, or they show a single bar in the center — that's a correction. The bottom bar sits 3 to 4 inches from the bottom of the footing, and your detail should show that explicitly.
Anchor bolt spacing catches a lot of contractors, especially on remodels where the existing foundation is being used. R403.1.6 requires anchor bolts at 6 feet on center maximum, within 12 inches of the end of each plate piece, and within 12 inches of a splice or corner. When a contractor dimensions the anchor bolts but doesn't call out the end-of-plate requirement, the plan-checker will red-line it.
Plate washers trip up plans in seismic zones. In SDC D0 through D2, the mudsill anchor bolts along braced wall lines require 3-inch by 3-inch by 0.229-inch plate washers. A lot of drawings either omit plate washers entirely or only call for standard cut washers. The plan-checker knows the difference and will flag it. If you're in a higher seismic zone, the washer spec is non-negotiable.
The official code
California Residential Code Chapter 4 — Foundations (DGS Building Standards Commission)
Read the source →