What this code requires
CBC 1803.6 sets what goes in the geotechnical (soils) report and when it is due. Where a geotechnical investigation is required, the permit applicant must submit a written report to the building official at the time of permit application. The report must include a plot of the investigation locations, the boring and penetration test logs, the soil profile, the water table elevation if encountered, foundation type and design criteria such as bearing capacity and how to handle expansive soil, liquefaction and differential settlement, and expected total and differential settlement. Investigations are required under Section 1803, for example for structures in Seismic Design Category C through F, unless the building official waives one.
How to fix it
Confirm your project needs a geotechnical report
Read the correction and the jurisdiction's submittal requirements. CBC 1803.2 calls for a geotechnical investigation and lets the building official waive it where satisfactory data from adjacent areas shows one is not needed, and 1803.5 lists conditions it must address, including questionable soil, expansive soil and structures in Seismic Design Category C through F. If you are unsure, ask the building department whether your project needs a report before the foundation is designed, not after the first correction.
Submit the full report with the permit application
CBC 1803.6 requires the written report to be submitted to the building official by the permit applicant at the time of permit application. Upload the complete signed report with the first submittal, not an excerpt or a cover letter. Reference it by firm, report number and date in the structural general notes so the reviewer can tie the drawings to it.
Check the report against the 1803.6 contents list
Before you submit, confirm the report includes a plot showing where the soil investigations were done, the boring and penetration test logs and soil samples, the soil profile, the water table elevation if encountered, foundation type and design criteria (bearing capacity, expansive soil mitigation, liquefaction, differential settlement and varying soil strength, and the effects of adjacent loads), and expected total and differential settlement. Where it applies, it also needs deep foundation information, special provisions for expansive soil, and compacted fill or controlled low-strength material properties and testing. If an item is missing, ask the geotechnical engineer for an addendum.
Carry the report's numbers onto the foundation plan
Cross-check the allowable bearing pressure, footing depth and width, slab and moisture recommendations, and any expansive soil or fill provisions in the report against the foundation plan and structural calculations. If the structural engineer designed to 2,000 psf and the soils report allows 1,500 psf, you have a discrepancy that must be resolved in writing before permit issuance. CBC 1806.2 does not let design values exceed the presumptive values in Table 1806.2 unless data to substantiate higher values are submitted and approved.
Add the soils special inspection note where it applies
Where special inspections apply, add a general note on the foundation plan sheet that reads something like: 'Soils special inspection per CBC 1705.6 and Table 1705.6: verify materials below shallow foundations are adequate to achieve the design bearing capacity, and verify excavations are extended to proper depth and have reached proper material, per the approved geotechnical report.' List the same items in the statement of special inspections, which CBC 1704.2.3 requires as a condition of permit issuance. If the report asks for the geotechnical engineer to observe the footing excavations, repeat that requirement in the note.
Get a written update when the design or site changes
If the foundation design changes after the report was written, or the site has been graded or filled since, ask the geotechnical engineer for a signed update letter or addendum that addresses the change, and submit it with the revised drawings. A letter confirming the original recommendations still apply is often enough when nothing material has changed. If the update changes a recommendation, the foundation plan has to be revised to match.
Resubmit with page and sheet references
In the response letter, cite the report by firm, number and date, give the report page where each 1803.6 item appears, and point to the sheet and note where its recommendations are carried into the foundation design. Cloud the revised notes on the foundation plan. A reviewer who can find each item in one pass clears the correction faster than one who has to hunt through a 40-page report.
Take the CBC 1803.6 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
The most common reason plans get flagged on CBC 1803.6 is that the soils report is missing from the submittal. The section requires the report to be submitted by the permit applicant at the time of permit application, so a reviewer who sees a foundation designed to specific soil values with no report in the file will stop and ask for it.
A second scenario is a report that is missing required contents. A short letter that states a bearing value but has no boring logs, no plot of where the borings were taken, no soil profile or no settlement estimate does not meet the list in 1803.6. Plan-checkers also flag reports that are silent on expansive soil or liquefaction when the site conditions call for it, and reports that leave out compacted fill specifications when the footings will bear on fill.
A third is a mismatch between the report and the drawings. The report recommends a footing type, depth, bearing value or slab treatment, and the foundation plan or structural calculations use something different. Plan-checkers compare the two. Under CBC 1806.2, a bearing value higher than the code's presumptive values needs approved data to back it, so a foundation designed to a higher pressure than the report allows draws a correction until the drawings or the report are revised in writing.
A fourth is construction-phase follow-through. Where special inspections apply, CBC 1705.6 and Table 1705.6 call for verifying that materials below shallow foundations can achieve the design bearing capacity and that excavations reach proper depth and material, judged against the approved geotechnical report. When the report recommends that the geotechnical engineer observe the footing excavations, reviewers often ask for that to be noted on the foundation plan and listed in the statement of special inspections. That observation comes from special inspection and the report's own recommendations, not from 1803.6.
The official code
California Building Code 2025 (Title 24 Part 2), Section 1803.6 Reporting, geotechnical report contents