What this code requires
CMC 504.4 is the California Mechanical Code section that governs how clothes dryer exhaust ducts must be built and routed. The duct must be rigid metal (no flexible plastic or foil), at least 4 inches in diameter, with a smooth interior and a maximum total run of 14 feet from the dryer connection to the exterior termination. That 14 feet already includes two 90-degree elbows, and each 90-degree elbow beyond two takes 2 feet off it, and screws are prohibited inside duct joints because they catch lint and create a fire hazard. Residential and multi-unit laundry rooms both hit this one.
How to fix it
Add a dryer exhaust duct route to the mechanical plan sheet
Draw a single-line diagram showing the complete path from the dryer connection to the exterior termination cap. Label the duct as 4-inch diameter rigid metal. Note the material spec (galvanized steel or aluminum, smooth interior). If you are submitting a set without a dedicated mechanical sheet, add a notation on the floor plan or laundry room detail. The duct route must be explicitly shown, not implied from the appliance location.
Calculate the allowed duct length and show your math on the plans
Add up the combined horizontal and vertical length of the duct and count the 90-degree elbows. The limit is 14 feet, and that already includes two 90-degree elbows. Take 2 feet off the 14 feet for each 90-degree elbow beyond two (CMC 504.4.2.1). If the run is still too long, shorten it or remove elbows. A longer run is allowed only where the dryer manufacturer's installation instructions permit it and the building department approves, or with a listed dryer exhaust duct power ventilator installed per its instructions (CMC 504.4.2.3). Show the calculation in a notes block on the plan sheet so the checker does not have to do it themselves.
Specify rigid metal duct throughout the concealed run
The concealed portion of the exhaust duct (inside walls, floors, or ceilings) must be rigid metal. Acceptable materials are galvanized steel or aluminum with a smooth interior surface. Corrugated metal flex, flexible foil, and plastic ducts are not allowed in concealed spaces. A listed transition duct up to 6 feet long may connect the dryer to the rigid duct, but it must not be concealed within construction (CMC 504.4.2.2). Call out the duct material on the plan sheet.
Remove all screws from duct joint details
Duct joints in a dryer exhaust run must not be fastened with sheet metal screws or similar fasteners that protrude into the duct interior. Screws catch lint, restrict airflow, and create fire hazards over time. If your plan details show screw connections, revise them to show approved slip joints with any sheet metal screws on the exterior only, or use foil tape rated for high-temperature dryer exhaust applications. Plan checkers look for screw symbols or notes in duct details, so make the detail explicit about fastener placement.
Show the exterior termination cap location and clearances
The dryer exhaust must terminate at an exterior wall cap with a backdraft damper. Mark the cap location on the exterior elevation and note the 3-foot minimum clearance from openings into the building (windows, doors) and from the property line. The cap must not have a screen, so a screened louvered vent will not pass. Some cities require notation of the cap model number or listing. If the duct exits through the roof, it needs a listed roof cap, but terminating through a sidewall is preferred and easier to maintain.
Address any fire-rated assembly penetrations
Where the rigid metal duct passes through a fire-rated wall or floor assembly, show a listed fire-stop collar or intumescent wrap at the penetration. Mark these penetrations on the plan and show the clearance or collar detail. This is a common secondary correction that comes back with the dryer duct response, so address it in the initial resubmittal rather than waiting for another round.
Revision-cloud every sheet changed for CMC 504.4
When you respond to the correction letter, draw a revision cloud with a delta triangle around every sheet where you made changes. Checkers in Orange County and Anaheim review corrections against the prior submission, not a fresh set. If they cannot quickly identify what changed, they may re-flag the same issue. A clean revision cloud on each affected sheet speeds turnaround and reduces the chance of a third correction on the same section.
Take the CMC 504.4 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Plan-checkers flag CMC 504.4 for a handful of specific reasons, and most corrections letters cite more than one at the same time.
The most common issue is a missing or incomplete duct route on the plans. If the mechanical plan sheet does not show a single-line diagram of the dryer exhaust path from the appliance to the exterior termination point, the checker will not approve it. Showing only the dryer location is not enough. The route, the duct diameter, and the duct material all need to be called out. First-time submissions skip this because the architect or designer focuses on the equipment schedule and forgets the duct routing diagram entirely.
The second common trigger is exceeding the 14-foot maximum. Many laundry rooms in tract homes and ADUs are located away from an exterior wall, and the duct has to travel through a wall cavity or ceiling before it terminates outside. Once you add a 90-degree turn at the appliance connection, another at the wall penetration, and account for the horizontal run, you are often at 12 to 16 feet. The 14 feet already includes two 90-degree elbows, and each 90-degree elbow beyond two takes 2 feet off the limit, so a run with three elbows is capped at 12 feet and a run with four at 10 feet (CMC 504.4.2.1). Checkers measure the combined horizontal and vertical length from your plans and count the elbows, not the straight-line distance.
A third failure pattern shows up in renovation permits where the existing duct material is flexible foil or corrugated plastic. CMC 504.4 requires rigid metal for the concealed portion of the run. If your plans show or imply a flex duct connection inside the wall cavity, expect a correction. The flexible transition section from the dryer itself may be short and allowable, but the moment it enters the wall, it must be rigid.
The official code
2025 California Mechanical Code Part 4 — Section 504.4 Clothes Dryers
Read the source →