What this code requires
CBC 11B-404.2.3 is the California Building Code section that sets the minimum clear width for accessible doors. The door opening must provide 32 inches of clear width when open 90 degrees, and its companion section, 11B-404.2.4, requires clear floor space on the approach side so a wheelchair user can operate the latch without being in the door swing. These sections apply to any project that includes an accessible route, which covers most commercial, public-use, and public housing buildings as well as tenant improvements and additions.
How to fix it
Verify the actual clear width in the door schedule
A 36-inch nominal door typically yields about 33.5 to 34 inches clear — enough to pass. A 32-inch nominal door rarely makes 32 inches clear after accounting for the door edge and stop, and a 30-inch door won’t come close. Update your door schedule to include a ‘clear width @ 90 deg open’ column and confirm every door on an accessible route meets 32 inches minimum. If a door barely passes, note the measured clear width on the schedule so the plan-checker doesn’t have to calculate it.
Add a door-approach maneuvering clearance diagram
Section 11B-404.2.4 has a table of maneuvering clearances (Table 11B-404.2.4.1) that vary by approach direction (front, hinge side, latch side) and operation type (push vs. pull). The most common case is front-approach pull, which needs 18 inches of clear floor space on the latch side and 60 inches of depth from the face of the door. Put a dimensioned diagram on your accessibility details sheet (often A0.2 or AD1) showing the actual approach clearances for each door on the accessible route. This one diagram eliminates most door-approach corrections.
Check for obstructions in the maneuvering clearance zone
Maneuvering clearances must be free of any obstruction. Check the plan at the latch-side approach for millwork, lockers, columns, electrical panels, or anything else that reduces the clear floor space. This is especially common in restrooms where a paper towel dispenser, sanitary napkin dispenser, or cabinet is installed near the door. If an obstruction is there, either move it or redesign the door approach. Annotate the plan to note ‘no obstructions within maneuvering clearance zone.’
Address threshold height at the accessible door
11B-404.2.5 (companion to 404.2.3) limits thresholds to 1/2 inch maximum, and changes in level between 1/4 and 1/2 inch must be beveled no steeper than 1:2. If your accessible door has a raised threshold, saddle, or transition between floor finishes that creates a raised edge, detail the transition on the plans. A common miss is a tile-to-carpet transition at a restroom door with a threshold strip — plan-checkers will flag both the threshold height and the clear-width at the same time.
Note door hardware type on the accessible route
11B-404.2.7 requires door hardware to comply with 11B-309.4: operable with one hand, without tight grasping, pinching or twisting of the wrist, and mounted 34 to 44 inches above the floor. That rules out twist knobs. If your plan shows ‘hardware by owner’ or just calls out a lock set without specifying the type, the plan-checker may flag it under 11B-404. Call out lever hardware specifically in the door schedule or hardware spec. Panic hardware on exit doors is generally compliant, but confirm it operates without tight grasping.
Document path-of-travel cost if this is a tenant improvement
On tenant improvements, renovations, and additions, California requires an accessible path of travel to the altered area; when the adjusted construction cost is at or under the valuation threshold, that path-of-travel work is capped at 20% of the adjusted construction cost. If the correction involves widening an existing door opening (rather than just updating plans), you may need to provide a path-of-travel cost analysis showing how much of the 20% budget is being spent on accessibility. This is a frequent add-on correction: the plan-checker cites 11B-404.2.3 for the door and then separately requests the path-of-travel disproportionate cost analysis. Get ahead of it by including the analysis in the original submittal.
Resubmit with a marked correction cloud on each affected detail
When you resubmit, draw a revision cloud around every sheet change and add a revision note referencing the correction letter item number. Plan-checkers review hundreds of sheets — without a cloud, they may not find the fix and the project gets a third-round correction for something you already addressed. Use revision triangle deltas with the submission number (Rev 2 or Rev 3) so the review history is clear.
Take the CBC 11B-404.2.3 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Here’s why plan-checkers flag 11B-404.2.3: the 32-inch clear width and the maneuvering clearance are two separate requirements, and it’s common to address one and miss the other entirely.
The most frequent correction involves the door leaf width itself. A 36-inch door does not automatically provide 32 inches of clear width. Stop-to-face of leaf, the door edge, and hardware projections all eat into the opening. The plan-checker measures the clear dimension with the door open 90 degrees, and plans that just note "36-inch door" without showing the resulting clear width get flagged. Put the clear-width callout on the door schedule or the accessibility detail.
The second common trigger is maneuvering clearance on the latch side. For a front-approach pull side, Table 11B-404.2.4.1 requires 18 inches of clear floor space on the latch side (24 inches for some door types). Plans that show a door opening into a corridor often forget that adjacent walls, built-in millwork, or lockers can eat into this clearance. The plan-checker will dimension it and if there’s 12 inches of latch-side clear instead of 18, the project gets a correction.
A third scenario crops up on renovation projects where an existing door is being replaced but the rough opening stays the same. A 34-inch rough opening can’t hit 32 inches of clear width after accounting for the frame and stops. The contractor has to either widen the opening or document that the path of travel obligation is triggered and document what portion of cost that represents. Plans that skip this analysis catch a 11B-404.2.3 flag almost every time.
The official code
California Building Code Title 24, Part 2, Chapter 11B — Accessible Doors and Gates (DSA/BSC landing page)
Read the source →