What this code requires
CPC 422.1 is the California Plumbing Code section that sets the minimum number of plumbing fixtures a building must provide based on its occupant load and use type. The calculation determines how many water closets, lavatories, drinking fountains, and service sinks are required before a permit can pass plan check. If your fixture schedule does not include an occupant load calculation tied to the required fixture count, or if the count comes in short, you will get flagged under CPC 422.1.
How to fix it
Determine the occupant load for each occupancy zone
Look up the occupant load factor for your building use type from the applicable code table. Divide the floor area of each occupancy zone (gross or net, as the table specifies) by its load factor to get the design occupant count for that zone. For example, an office area at 3,000 sq ft at 150 sq ft per occupant gives 20 occupants. A restaurant dining area at 1,200 sq ft at 15 sq ft per occupant gives 80 occupants. For mixed-use buildings, calculate each zone separately and do not combine them under a single occupancy factor. Show the calculation on the plans.
Split occupant count by gender for water closet calculation
CPC 422.1 calculates water closet requirements separately for male and female occupants. The default split is 50 percent male and 50 percent female unless submitted information shows a different distribution. Take each zone total occupant count, divide in half, and apply the gender-specific water closet ratios from CPC Table 422.1. Note that urinals may substitute for a portion of male water closets in certain occupancies, but only if the urinals appear on the fixture schedule with the substitution math documented alongside.
Apply CPC Table 422.1 minimum ratios for all fixture types
CPC Table 422.1 specifies the minimum fixture count per type based on occupancy classification and occupant population. Read across the row for your occupancy, find the ratio (for example, 1 water closet per X occupants), and divide your occupant count by that ratio. Always round fractions up to the next whole number; for multiple occupancies, sum the fractions first and then round up (CPC 422.1.1). Apply this process to every fixture type: water closets, lavatories, drinking fountains (unless your occupancy qualifies for an exemption), and service sinks for janitorial use. Having extra of one type does not offset a shortfall in another.
Build a fixture count table directly on the plumbing sheets
Put the math on the plans, not just the fixture list. The fixture count table should include: occupancy type, gross floor area, occupant load factor, calculated occupant count, male/female split, minimum required per fixture type from Table 422.1, and count provided. A tabular format on sheet P1 or P0 with one row per occupancy zone and summed totals works well. For mixed-use buildings, break out each zone in its own row. The plan-checker needs to trace your arithmetic without making assumptions about what you intended.
Confirm every fixture type independently meets or exceeds the minimum
Walk the fixture table row by row: water closets provided vs. required, lavatories provided vs. required, and so on for every type. Every category must independently meet or exceed the minimum. Adding an extra toilet does not make up for a missing lavatory. If any row comes up short, add the fixture to the floor plan before resubmitting. Use fixture tags on the floor plan that match the fixture schedule so the checker can cross-reference a specific room without hunting through the plans.
Calculate ADU and accessory dwelling units as separate entities
If the project includes an ADU, junior ADU, or detached accessory structure with plumbing, calculate that unit fixture count independently. An ADU is a separate dwelling unit, not an extension of the primary house. For a studio or 1-bedroom ADU, the typical minimums are 1 water closet, 1 lavatory, 1 kitchen sink, and 1 bathing fixture. Table 422.1 also lists an automatic clothes washer connection for one- and two-family dwellings, so confirm with your jurisdiction whether the ADU needs its own. Show the ADU fixture schedule separately from the primary dwelling schedule. This applies even when both units share a single permit.
Attach a concise response note when resubmitting
When you resubmit after a CPC 422.1 correction, include a short response letter that calls out the sheet and schedule where the fix appears. Something direct: "CPC 422.1 addressed. See Sheet P1.1, Fixture Count Schedule, for updated occupant load basis and revised fixture totals." Plan-checkers reviewing a resubmittal are working through a stack of projects. A direct pointer to the fix saves them time and reduces the risk of a second correction round on the same item just because the revision was hard to find.
Take the CPC 422.1 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Plan-checkers flag CPC 422.1 when the fixture schedule on the plumbing sheets does not match the calculated occupant load. The most common case: you have specified the fixtures your client wants but did not show the math proving you hit the minimum. A 2,000-square-foot office addition might need 1 water closet for the first 15 females and 1 for the first 50 males, plus lavatories at 1 for the first 50 females and 75 males — but if the plans just list "2 toilets, 2 sinks" with no occupant load basis, the checker cannot verify compliance and the correction is automatic.
The second scenario comes up on occupancy changes, which Table 422.1 covers whenever the change increases the occupant load. If you are converting a retail space into a restaurant, the occupant load factor changes dramatically — the fixture count follows, and plans that carry over the retail fixture count without recalculating for the new use fail every time.
Mixed-use buildings are another consistent source of corrections. Each occupancy type (office, retail, assembly) carries a different occupant load factor, and the fixture calculation must be broken out by use. Lumping the whole floor area under one occupancy type understates the required fixture count for the denser zones.
ADU additions also trip this section when the ADU plumbing is treated as part of the primary dwelling instead of as a separate dwelling unit. Each unit needs its own fixture count verified against the Table 422.1 minimum for a dwelling.
The official code
2025 California Plumbing Code (CPC) Section 422.1 and Table 422.1, Minimum Plumbing Facilities, California Building Standards Commission