Building Code Reference

Got a CPC 1101.12 correction?

Storm drainage sizing

For builders in California, Greater Seattle, the Las Vegas area, the Denver area and Kansas City · CrossBeam Permits

What this code requires, how to fix it, and how cities and counties review it

What this code requires

CPC 1101.12 is the California Plumbing Code section that requires roof drains, overflow drains, and storm leaders to be sized for the local rainfall rate using the code’s published drainage tables. Every square foot of roof area must route to a drain sized to handle the peak design storm for your specific location. Single-family additions, ADUs, and commercial re-roofs all trigger this requirement whenever drainage work is part of the permit scope.

How to fix it

  1. Confirm your jurisdiction’s design rainfall rate

    Look up the 60-minute, 100-year design rainfall intensity (in inches per hour) for your project city in CPC Table D 101.1 (Appendix D). Its California entries range from 1.3 in/hr (Lake Tahoe) to 3.0 in/hr (Palmdale), with Los Angeles at 2.0. The zone for your project determines every downstream pipe size. If you’re not sure which zone applies, the plan-checker’s correction letter will often name it — or your civil engineer can pull it from the National Weather Service TP-40/NOAA Atlas 14 data for the site coordinates.

  2. Calculate the total roof area draining to each outlet

    Measure the horizontal projected area (not the slope area) of every roof surface draining to each drain or scupper. For sloped roofs, use the plan-view footprint, not the rafter length. Count any area where water will concentrate: skylights, equipment pads, and parapet pockets all count. If multiple roof levels drain to a common leader, add those areas together. Document each sub-area on the plans so the reviewer can follow your math without calling you.

  3. Size roof drains and vertical leaders using CPC Table 1103.1

    CPC Table 1103.1 sizes vertical conductors and leaders by projected roof area at your design rainfall rate, and Table 1103.2 does the same for horizontal storm drains by pipe diameter and slope. Work through it in sequence: area (sq ft) x rainfall rate (in/hr) / 96.23 gives you the required GPM per outlet, then match that GPM to a pipe size in the vertical-leader table. Most residential leaders end up at 3 or 4 inches, but in high-rainfall zones a single large roof may need 5 or 6 inches. Show the calculation on the plans — a table format with area, GPM, pipe size, and table reference is what reviewers expect.

  4. Size horizontal storm conductors for slope and flow

    Once you have the vertical leader size, continue through the CPC horizontal-conductor sizing table. Pipe size depends on both GPM and slope — a 4-inch pipe at 1/8 inch per foot carries significantly less than at 1/4 inch per foot. Label the slope on every horizontal run in the plans. If you can’t achieve the minimum slope shown in the table due to structural constraints, increase the pipe size to the next diameter that covers your GPM at the flatter slope.

  5. Add overflow drains or scuppers sized for the same flow

    CPC 1101.12.2 requires secondary (emergency) roof drainage by scuppers, an open side, or secondary roof drains set at least 2 inches above the roof surface. A separate secondary piping system is sized for the same rainfall rate as the primary system, but if secondary drains tie into the primary conductor, the combined system must be sized for double the local rainfall rate. Scuppers must be at least 4 inches high and as wide as the circumference of the required roof drain. Show both the primary and overflow systems on the roof plan with callouts for size and type.

  6. Label drain types and pipe materials on the plans

    CPC 1101.12 corrections sometimes come back a second time because the first resubmit fixed the sizing but didn’t identify drain types. Call out each drain as “roof drain,” “overflow drain,” or “area drain” on the plan. Note the material (cast iron, PVC, or other approved material per CPC Chapter 11) and the connection method. Roof drain bodies need to match the pipe material downstream, and some cities have local amendments requiring cast iron for the first 4 feet of leader below a roof drain.

  7. Include a drainage calculations note block on the plans

    Put a simple table directly on the plumbing or civil sheet: list each drain by ID, contributing area in square feet, design rainfall intensity in in/hr, required GPM, selected pipe size, and the CPC table used. This format gives the reviewer everything they need in one place and avoids the back-and-forth of a comment asking where the calculation is. If a civil engineer stamped the drainage design, include their stamp and license number on the same sheet.

  8. Resubmit with a written response addressing each correction item

    When you resubmit the revised plans, attach a written response to each correction item that cited CPC 1101.12. Reference the sheet and detail number where each fix appears. Plan-checkers reviewing a resubmit spend less time on sets that map each correction to a specific plan location — it’s not required, but it consistently shortens the review cycle.

Take the CPC 1101.12 fix steps with you

All 8 steps in one email, so you have them on site instead of on this page.

Why you got flagged

Plan-checkers flag CPC 1101.12 when storm drainage calculations are missing entirely from a set. Roof drainage is often treated as an afterthought on residential additions — the architect draws in a generic 4-inch leader without referencing the rainfall tables, and the plumbing reviewer sends it back. No calculation, no approval.

A second common scenario is using a flat default pipe size when the local design rainfall rate makes that size undersized. California’s hourly rainfall intensity varies from under one inch in the dry interior valleys to over four inches along parts of the North Coast. A 4-inch vertical leader that handles 3,450 square feet in a low-rainfall zone might only handle 1,500 square feet in a high-intensity zone. Getting the zone wrong means the plans show a system that will overflow during a design storm.

Overflow drain omission is another frequent flag. When a primary roof drain clogs, water needs somewhere to go before it pondes enough to exceed the structural load limit. If the plans show primary drains but no overflow drains or scuppers, the plan-checker will cite 1101.12 even if the primary drain sizing is correct.

A fourth trigger is re-roofing permits that add or relocate drains without updating the drainage calculations. The reviewer will ask for revised sizing to confirm the new drain layout matches the code tables for your jurisdiction’s rainfall zone.

The official code

California Plumbing Code — Part 5 of Title 24 (Building Standards Commission)

Read the source →

Common questions

What rainfall rate do I use for storm drain sizing in California?
Unless the building department requires otherwise, use the 60-minute, 100-year rainfall rate for your project location from CPC Table D 101.1 (Appendix D). Its California entries run from 1.3 in/hr (Lake Tahoe) to 3.0 in/hr (Palmdale): Los Angeles is 2.0, Lucerne Valley 2.5, and Eureka, Needles, San Diego and San Francisco 1.5. The correct zone matters because it directly sets your required GPM, which drives pipe diameter. Using a national default or the wrong zone is one of the main reasons CPC 1101.12 corrections come back a second time.
Does CPC 1101.12 apply to ADU projects?
Yes, if the ADU includes any new roof area or modifies existing drainage. A detached ADU with a new roof needs storm drainage sized per CPC 1101.12 just like any new structure. An attached ADU that adds roof area to an existing building may require you to revisit the existing drainage system to confirm the added area does not overload the existing leaders. Where the existing system is already at capacity and the ADU adds significant area, you may need to run a separate leader to a new outlet.
Do I need overflow drains on every roof?
Not necessarily on every roof, but on any roof where water could accumulate if the primary drain clogs. Flat or low-slope roofs with parapets are the most common case. If your roof has free-draining edges on all sides with no barriers, ponding before overflow is not possible and a secondary overflow system may not be required. But if there is any parapet, curb, or raised edge that could hold water, you need overflow protection. When in doubt, show an overflow drain or scupper — it’s far cheaper than a second corrections cycle.
Can I use PVC pipe for storm drain leaders under a roof?
CPC Chapter 11 lists approved materials for storm drainage, and PVC (Schedule 40 or Schedule 80) is generally permitted for above-ground storm leaders. Some local amendments, particularly in older dense urban areas, require cast iron for the first few feet below the roof drain body to reduce noise and improve fire resistance. Check your city’s local amendments before specifying materials. If the project is in LA or San Francisco, the local amendments are worth a specific look — both cities have requirements that differ from the base CPC.
What is the formula for calculating required drain GPM from roof area?
The standard formula used with CPC tables is: GPM = (roof area in sq ft x rainfall intensity in in/hr) / 96.23. The 96.23 is a unit-conversion constant that converts the volume to gallons per minute. For example, a 2,000 sq ft roof in a 2.5 in/hr zone requires about 52 GPM per drain (2,000 x 2.5 / 96.23 = 51.96 GPM). Look up 52 GPM in the CPC vertical-leader table to find the minimum pipe diameter. Show this arithmetic on your plans — reviewers expect to see area, rate, GPM, and pipe size in a table or note block.
What if my horizontal drain pipe cannot slope at the minimum grade?
Go up a pipe size. The CPC horizontal-conductor tables show allowable GPM at different slopes, typically 1/8 and 1/4 inch per foot. If your structural constraints limit you to 1/8 inch per foot and the table shows that diameter is undersized at that slope, move to the next diameter up. You can also combine runs differently to reduce the GPM burden on any single run, but that adds design complexity. Document whatever slope you are using and show it explicitly on the plans so the reviewer does not have to calculate it from invert elevations.
Does storm drainage have to be separate from the sanitary sewer?
Yes. Storm drainage must stay completely separate from the sanitary sewer system under CPC requirements. Roof leaders and area drains discharge to a storm drain, a dry well, a French drain, an infiltration basin, or direct surface discharge to a public right-of-way — none of which connect to the sanitary system. Cross-connections between storm and sanitary piping are a serious code violation and a public health concern. If your site has no storm drain connection and cannot discharge to grade, you will need to design a retention or infiltration system, which may also trigger CALGreen stormwater requirements.