What this code requires
CEC Article 225 governs feeders and branch circuits that run outside to detached structures — a second building on the same property such as a garage, ADU, workshop, or barn. When you add a sub-panel to a detached structure, Article 225 requires that the feeder be sized for the calculated load of that structure, that conductor size, conduit type, overcurrent protection, and grounding electrode system all be shown on the electrical plans. Most plan-check corrections on this section come down to one issue: the plans don't show the feeder details or the load calculation, so the plan checker can't verify the sub-panel is adequately protected.
How to fix it
Run a load calculation for the detached structure
Calculate the total connected load for every circuit in the detached structure. Use the standard load calculation method: general lighting at 3 VA per square foot, small-appliance circuits at 1,500 VA each, and nameplate ratings for any fixed appliances (air compressor, welder, EV charger). Apply the demand factors from CEC Article 220 where allowed. The result is the minimum feeder ampacity you must design to. Show the calculation on a dedicated electrical plan sheet — a hand-written note saying 'feeder per load' will not pass.
Size the feeder conductors to the calculated load
Select conductor gauge from CEC Table 310.16 based on the calculated ampacity, derated for conduit fill and ambient temperature if needed. For a typical detached garage sub-panel in Southern California climate, #6 AWG copper in 1-inch conduit handles up to 65A continuous, #4 AWG handles up to 85A, and #2 AWG handles up to 115A. If the run is long (over 100 feet), check voltage drop — keep it under 3% for the feeder alone. Note the conductor material (copper vs. aluminum), gauge, and conduit type on the electrical plan and panel schedule.
Specify overcurrent protection at the source panel
The OCPD at the main panel must match or be smaller than the feeder conductor's ampacity rating. A 60A breaker protecting #6 AWG copper is correct. A 100A breaker on #6 AWG is a CEC 240.4 violation. Show the breaker size, pole count (2-pole for 240V feeders), and manufacturer slot in the panel schedule on your plans. If the main panel doesn't have capacity for a new 2-pole breaker, note that a panel upgrade or load management is required before the feeder can be added.
Design a disconnect at the detached structure
CEC 225.31 requires a disconnect means at each building or structure. CEC 225.39 sets the minimum disconnect rating: 15A for a single branch circuit, 30A for two 2-wire branch circuits, 100A 3-wire for a one-family dwelling, and 60A for all others. The disconnect can be a main breaker in the sub-panel or a separate disconnect switch. Show the disconnect location and rating on the site plan and electrical plan. For ADUs, the disconnect is typically the main breaker in the sub-panel mounted on an exterior wall near the entry.
Install and document the grounding electrode system
A detached structure served by a feeder from another building needs its own grounding electrode system at the structure — it cannot share the main building's grounding electrodes. Per CEC 250.32(A), install two ground rods at least six feet apart (or one rod with verified 25-ohm or less resistance), connect them with a grounding electrode conductor sized per CEC Table 250.66, and bond it to the grounded neutral bus only if no equipment grounding conductor is run in the feeder. Show the ground rod locations, conductor size, and bonding connections on the electrical plan. This is one of the most commonly missed items on detached-structure corrections.
Specify conduit type and burial depth for underground runs
If the feeder runs underground between buildings, the plan must call out the conduit type and burial depth. PVC Schedule 40 or 80 requires 18-inch minimum burial depth under non-vehicle areas and under one- and two-family dwelling driveways, and 24 inches under streets and commercial driveways. Rigid metal conduit can be buried at 6 inches. Direct-bury cable (UF-B) requires 24 inches minimum under general areas and 18 inches under a 4-inch exterior concrete slab, and must be in a raceway under a building. Show a conduit schedule and a detail or note on the site plan indicating depth, conduit material, and any changes in depth at slab penetrations.
Update the panel schedule and one-line diagram
Many plan-check rejections on CEC 225 are purely a documentation problem. The plans may describe the right equipment but put the feeder details in the wrong place. The plan checker needs to see: (1) a one-line diagram showing the feeder from main panel to sub-panel, including conductor size, conduit, OCPD ratings, and sub-panel ampacity; (2) a panel schedule for the sub-panel listing each branch circuit, its load, and the breaker size; and (3) a notation referencing the load calculation. Put all of this on one sheet if possible so the reviewer doesn't have to hunt across multiple pages.
Take the CEC 225 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Plan checkers flag CEC 225 most often when the electrical plans show a new sub-panel in a detached garage or ADU but don't include a feeder schedule. The reviewer needs to confirm the wire gauge, conduit type, and OCPD amperage match the calculated load — if that table isn't on the plans, the job gets a correction on the first pass.
A second common trigger is an undersized feeder. Contractors sometimes spec the feeder based on the panel amperage alone rather than running an actual load calculation. CEC 225.39 sets minimum disconnect sizes for detached structures (100A for a building with six or more branch circuits), and those figures are a floor, not a design target. If your 100A sub-panel feeds a workshop with a 3-HP air compressor, welder, and lighting circuits, a load calc may show you actually need a larger feeder.
Grounding and bonding is a third source of corrections. Detached structures require their own grounding electrode system — typically two ground rods spaced at least six feet apart — and a separate equipment grounding conductor in the feeder. Plans that show the sub-panel but omit the grounding detail will get flagged under CEC 225.30 and 250.32.
A fourth scenario applies specifically to ADUs: when a detached ADU is served from the main house panel, the feeder often crosses a property line or runs underground. The plans need to call out burial depth (24 inches for direct-bury cable, 6 inches for PVC conduit under a concrete slab per CEC 300.5), conduit material, and any required GFCI protection for the branch circuits inside the ADU. If any of those details are missing or inconsistent with the calculated load, the plan checker will send it back.
The official code
California Electrical Code (Title 24, Part 3) — Article 225: Outside Branch Circuits and Feeders
Read the source →