What this code requires
Title 24 CF2R is the California Energy Code installation certificate that a licensed contractor completes and signs after installing the energy features shown on the CF1R compliance report. It documents that items like insulation, windows, HVAC equipment, duct sealing, and water heating were actually installed to match the approved design. The building department will not schedule a final inspection — and the city will not grant a certificate of occupancy — until the CF2R is on file. Almost every new construction and significant residential renovation in California that requires a Title 24 energy analysis will also require a completed CF2R.
How to fix it
Identify which CF2R form version applies to your permit
Check the date you applied for the permit. If you applied on or after January 1, 2026, you need the 2025-cycle CF2R form. If you applied before that date, you're on an earlier cycle and need the form for the cycle in effect on your application date. The form version is printed in the header of each PDF. Download the current-cycle forms directly from the California Energy Commission compliance forms page at energy.ca.gov — don't reuse a saved copy from an older project. Using the wrong cycle version is a guaranteed rejection, and you won't know until the inspector turns you away at the final.
Pull the approved CF1R and compare every measure
The CF2R must match the CF1R that was approved with the permit. Pull the CF1R and go section by section: insulation R-values for the attic, walls, and floors; window U-factor and SHGC ratings; HVAC equipment efficiency (SEER2 or EER2 for cooling, AFUE or HSPF2 for heating); duct insulation level; and water heater UEF. The CF2R asks for actual installed product model numbers. If any spec you installed is lower than what the CF1R shows, stop — you have a compliance issue to resolve before the form can be completed honestly.
Fill out the installer sections with your CSLB license number
The installer portion of the CF2R requires the contractor's name, company, CSLB license number, and signature. Each trade that installed a covered measure fills out its own section. The HVAC contractor signs off on the mechanical equipment and duct sections. The insulation installer signs off on the insulation section. The window or door installer covers fenestration if that's in scope. Leaving any required section blank or unsigned is a rejection. Review the form instructions carefully to see which sections apply to your project scope.
Schedule an ECC-Rater if your CF1R lists verification measures
The CF1R will call out which measures require ECC field verification. Common ECC triggers include duct leakage testing (when ducts are installed or altered in conditioned space), refrigerant charge verification for certain split-system HVAC equipment, and airflow measurement. If any ECC measures appear on your CF1R, a certified ECC-Rater (formerly called a HERS rater) must visit the site, perform the required tests, and complete and register a Certificate of Verification (CF3R). Find a rater through an ECC-Provider approved by the California Energy Commission. Give yourself at least one to two weeks of lead time.
Submit the completed CF2R before calling for final inspection
Once all installer sections are signed, register the CF2R with the ECC-Provider data registry (required for low-rise residential) and make it available to the building department, and have the ECC-Rater (if required) register the CF3R, before calling for your final inspection. Some jurisdictions also want a copy at the job site. Confirm the submission method with your local building department ahead of time. Keep a copy for your project file — the inspector will likely want to review it during the final walk-through.
Resolve substituted products before completing the form
If you installed a product different from what the CF1R specifies, work out the compliance issue before putting pen to paper on the CF2R. If the substituted product meets or exceeds the spec (higher R-value, lower U-factor, higher SEER2), just list what was actually installed — that's fine. If it falls short, you have two paths: a registered compliance consultant re-runs the energy calculation with the actual product to show the project still passes Title 24 as a whole, or you install the originally specified material. Never fill out the CF2R with specs that don't match what's in the walls — that's a false certification and can trigger stop-work or require corrective work after the fact.
Keep the signed CF2R at the job site through the final inspection
Even after submitting the form electronically, keep a printed copy at the job site through the final. Many inspectors pull up the form on their tablet but also want to see the physical copy to compare what's in the building against what was certified. If the site copy is missing or shows different numbers than what was submitted to the city, the inspector can stop the inspection and require you to sort it out before they sign off. Having the form on site costs nothing; losing the final costs weeks.
Take the Title 24 CF2R fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Here's why plan-checkers flag CF2R: the most common trigger is simply that no CF2R was submitted with the permit documents at all. Many contractors treat the CF2R as something to worry about at final, not at submittal. But some jurisdictions require the forms to be attached during plan check, and even those that don't will catch the missing certificate when the inspector asks for it at the field inspection. Either way, a missing CF2R stops the clock.
A second common flag is a mismatch between the CF1R (the design compliance report) and the CF2R (what was actually installed). If your CF1R specifies R-38 attic insulation and the installed equipment listed on the CF2R shows R-30, the plan-checker will reject it. Same goes for windows: if the CF1R called out a U-factor of 0.28 and the CF2R lists a different product, you're getting flagged. The CF2R is supposed to confirm what was installed, not redo the energy design — if the numbers don't line up, something went wrong in the field.
A third scenario is an incomplete or unsigned CF2R. Each installing contractor must sign the CF2R sections for their work, and where field verification is required, the ECC-Rater completes a separate Certificate of Verification (CF3R) that depends on a registered CF2R. If an installer section is blank or unsigned, the certificate is not valid. Submitting a partial form is as bad as submitting no form at all.
Finally, watch for the wrong form version. California adopted new 2025 Energy Code forms for permits applied for on or after January 1, 2026. Submitting a 2022-cycle CF2R on a project that's on the 2025 cycle is an instant rejection. The cycle version must match the permit application date.