What this code requires
NFPA 13D is the national standard for residential fire sprinkler systems in one- and two-family dwellings and manufactured homes. In California, CRC R309 requires sprinklers in new one- and two-family dwellings, designed to NFPA 13D or the equivalent CRC R309.3, and in most ADUs. The standard specifies where heads go, how much water the system must supply, pipe sizing, and what gets into the deferred submittal. You’ll see it cited when the plan doesn’t show a deferred submittal note or when the hydraulic calculations are missing from the cover sheet.
How to fix it
Add a deferred submittal note to the cover sheet
On the cover sheet or general notes page, add a clearly labeled note that reads something like: 'Fire sprinkler system: Deferred submittal. Design, drawings, and hydraulic calculations to be submitted by a licensed C-16 contractor and approved prior to installation. System shall comply with NFPA 13D as adopted by the 2025 California Residential Code, Section R309.' This single note eliminates the most common NFPA 13D correction. The note doesn't have to be long — it just needs to exist and reference the correct code edition.
Reference the water supply source on the cover sheet
Include a brief note identifying the water supply type: domestic water meter, dedicated water storage tank, or combination. If pulling from the domestic supply, note the water purveyor (e.g., Anaheim Public Utilities or Southern California Water Company depending on your site). State that a water purveyor letter confirming static pressure and available flow will accompany the deferred submittal. You don’t need the hydraulic calcs at plan check, but you need to show the plan checker you know where the water is coming from.
Remove partial sprinkler head layouts or label them clearly
If you've sketched approximate sprinkler head locations on the floor plan as a placeholder, either remove them entirely or add a clearly visible note adjacent to the symbols: 'Sprinkler head locations shown for reference only. Final layout per deferred submittal by C-16 contractor.' Partial layouts without this note read as an incomplete submission. The cleaner move is often to remove the symbols entirely and let the deferred submittal handle all sprinkler placement.
Clarify the ADU sprinkler scope if an ADU is involved
When the permit includes a new ADU or a detached addition to an existing home, add a scope note explaining how the ADU will be served: (a) extension of the existing residential sprinkler system, (b) a new standalone NFPA 13D system for the ADU, or (c) a note that no sprinklers are required because the ADU meets the CRC R309.2 exception: the existing home is not sprinklered, the detached ADU is 1,200 sq ft or less, and it is on the same lot. Which option is correct depends on your project. What matters for plan check is that you’ve addressed it. Leaving the question open gets you a correction asking you to address it.
Verify your C-16 contractor is listed as deferred submittal responsible party
Some cities require the C-16 contractor's license number to appear on the cover sheet or in the deferred submittal note at the time of plan check, not just at deferred submittal review. Anaheim and Irvine both request this information upfront. Check the plan-check comment carefully — if the correction specifically asks for the contractor's license, add it to the cover sheet note. If your C-16 isn't selected yet, note 'C-16 contractor to be determined; license number provided with deferred submittal.'
Confirm the system type on the architectural drawings
NFPA 13D allows wet-pipe, dry-pipe, and antifreeze systems. Wet-pipe is standard for conditioned interior spaces. If any portion of the system runs through an unconditioned garage, attic, or crawlspace where freezing is a risk, you need to specify how that’s handled: heat tracing, drain-down, or a separate dry section. In coastal Orange County, freeze protection is rarely an issue, but document it anyway. A single sentence on the drawings is enough: ‘All sprinkler piping within conditioned space; wet-pipe system specified.’
Check that plans reference the current California-adopted NFPA 13D edition
California adopts NFPA 13D by reference through the California Residential Code. Your plans should reference the version incorporated into the currently adopted CRC — as of the 2025 CRC, that’s the 2025 edition of NFPA 13D, as amended in CRC Chapter 44. Plans that reference an older edition (e.g., NFPA 13D 2016) will get flagged. Update any general notes that cite the standard to match the current adopted edition. The Building Standards Commission publishes adoption tables at dgs.ca.gov/BSC/Codes.
Take the NFPA 13D fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Plan checkers flag NFPA 13D corrections for a handful of specific reasons, and most of them show up before a single pipe is sized.
The most common is a missing deferred submittal note. California requires fire sprinkler systems to be designed by a licensed C-16 contractor, so the permit set doesn’t need full sprinkler drawings at plan check — but it does need a note on the cover sheet acknowledging that a separate deferred submittal will be submitted and approved before installation begins. When that note is absent, the plans get kicked back.
Water supply documentation is the second most frequent hit. NFPA 13D requires the system to deliver water at the design flow rate for a minimum of 10 minutes. If your cover sheet or the preliminary fire sprinkler notes don’t reference the water supply source, static pressure, and residual flow test data from a water purveyor letter, expect a correction.
A third scenario involves scope creep on the design documents. Some contractors show partial sprinkler head locations on the floor plan — enough to suggest the system, but not enough to constitute a complete layout — and no note clarifying that the detail lives in the deferred package. Plan checkers read partial layouts as an incomplete submission rather than a placeholder, which triggers the same correction as omitting the note entirely.
Finally, ADU additions to existing homes often get flagged when the permit set doesn’t address whether the existing home’s system extends to the new unit or whether a separate system serves the ADU. NFPA 13D doesn’t require you to answer that question fully at plan check, but you need to at least acknowledge how the ADU will be served.
The official code
NFPA 13D Standard for the Installation of Sprinkler Systems in One- and Two-Family Dwellings and Manufactured Homes