What this code requires
CALGreen 4.106.4 requires every new single-family home to include a dedicated raceway for a future 208/240-volt EV charging circuit in the garage. The raceway — typically a 1-inch minimum conduit — must run from the electrical panel to an outlet box or junction box in the garage and be labeled "EV CAPABLE" at the panel. No charger hardware is required at the time of construction; the point is to rough in the path so a future EVSE can be wired without tearing into walls or the panel. This is a mandatory CalGreen measure — it applies to all new single-family homes statewide, with no exceptions for lot size, square footage, or garage type.
How to fix it
Confirm the raceway is shown on the electrical floor plan
On the electrical plan sheet (typically E1 or the combined electrical/mechanical sheet), draw a 1-inch minimum conduit home-run from the main electrical panel to the garage. Show the conduit as a dashed or annotated line with a note identifying it as the "EV-capable raceway per CALGreen 4.106.4." If your electrical plan doesn't have a garage detail, add one.
Show the termination point in the garage
At the garage end of the raceway, show an outlet box or junction box on the electrical plan. The box should be located on the wall near where an EVSE or receptacle would typically mount — typically 18 to 48 inches above the finished floor on the wall adjacent to the parking area. Add a note: "EV-capable outlet box, circuit reserved, see panel schedule."
Add "EV CAPABLE" label to the panel schedule
In the electrical panel schedule, reserve space for a two-pole breaker for a 40-ampere minimum, 208/240-volt dedicated branch circuit and label it "EV CAPABLE — CALGreen 4.106.4." If the breaker isn't installed yet (which is allowed), note it as a "future" or "spare" slot. The label on the panel schedule is what plan-checkers specifically look for.
Specify conduit size on the plan notes
The conduit must be at minimum 1 inch in diameter to allow future wire pull-through without wall demolition. Call this out in the electrical general notes: "EV-capable raceway: 1-inch minimum EMT or PVC conduit with pull string, from panel to garage outlet box per CALGreen Section 4.106.4." Some plan-checkers want to see the conduit material specified — EMT is common inside conditioned spaces, PVC where underground or exposed to weather.
Address detached garages separately
CALGreen 4.106.4.1 is written for one- and two-family dwellings and townhouses with attached private garages. If the garage is detached, ask the building department whether a local reach code or amendment still requires the raceway. If it does, show the conduit path on the site plan from the main panel (or the detached garage sub-panel) to the EV outlet box location, and note any future feeder or extension the run will need.
Cross-reference the CalGreen checklist on the cover sheet
Most jurisdictions require a CalGreen mandatory measures checklist on the cover sheet or a dedicated sheet. Find the 4.106.4 line item on the checklist and mark it as "complying" with a note pointing to the electrical sheet where the raceway is shown. Plan-checkers cross-reference the checklist against the drawings — if the checklist says complying but the drawings don't show the raceway, that's another correction.
Update the Title 24 CF1R if your energy consultant controls that document
Some energy consultants include EV-ready notes in the CF1R compliance document. If yours does, confirm the CF1R reflects the 4.106.4 raceway. The Title 24 energy compliance and CalGreen mandatory measures are reviewed together in most jurisdictions, and a mismatch between the two documents can trigger additional questions even after the electrical plans are corrected.
Take the CALGreen 4.106.4 fix steps with you
All 7 steps in one email, so you have them on site instead of on this page.
Why you got flagged
Here's why plan-checkers flag this section more often than contractors expect: the EV raceway is a newer mandatory measure that didn't exist in earlier CalGreen cycles, and it often falls through the cracks because it lives in the green-building chapter rather than the electrical plans where most reviewers look for it.
The most common correction is a simple omission. The electrical plans show the panel schedule, circuits, and subpanel if applicable, but the EV-capable raceway isn't drawn at all. No conduit home-run shown, no junction box or outlet box in the garage, no note on the panel schedule. Plan-checkers look specifically for the "EV CAPABLE" label on the panel diagram, and when it's missing, the correction goes out. This catches a lot of designers who learned electrical drafting before 4.106.4 took effect.
A second pattern: the raceway is shown but the panel label is missing. The conduit is drawn correctly from panel to garage, but the panel schedule doesn't call out the reserved breaker slot or the "EV CAPABLE" designation. The city catches the disconnect between the conduit line on the floor plan and the unmarked panel schedule. Still triggers a corrections letter and another review cycle.
Third pattern: the raceway terminates incorrectly. Some plans show the conduit ending at a blank wall rather than at an outlet box or junction box. CalGreen requires a proper termination point; the pull string alone isn't enough. If a future electrician can't terminate an EVSE cable or receptacle there without fishing new wire, the design doesn't meet the intent of the section.
A fourth issue comes up on detached garages. The state section, 4.106.4.1, is written for dwellings and townhouses with attached private garages, but some cities extend EV requirements through local amendments. If the garage is detached, confirm the local rule before you leave the raceway off, and note the basis on the plans.
The official code
2025 California Green Building Standards Code (CALGreen) — Section 4.106.4, Residential Mandatory Measures
Read the source →